What is the asphalt mixing plant process guidelines

To build road with high quality which can stand heavy weight, sun light, the rain, the wind, the snow, the asphalt quality is very significant. Then if we want to get qualified asphalt, the asphalt mixing plant process producing need more attention, there are many points during the production, we are going to talk about them step by step. 
asphalt mixing plant process
1, ignition drying the cylinder and increase the temperature of the dust chamber first, the throttle size depends on various specific circumstances, such as weather, temperature, mix grading, aggregate moisture content, dust room temperature, hot aggregate temperature and the equipment, the flame must be manually controlled. 
2, until all parts reach the appropriate temperature, began to charging the aggregate, and pay attention to whether the transport of the belt is normal. 
3, until the aggregate is transported to the aggregate weighing bucket, pay attention to observe whether the difference between the load cell readings and rating is within the allowable range, if the difference is very large, we should take appropriate measures. 
4, load locomotives should be placed ready at the waste (spill) mouth, the waste (spill) should be pour out of the court. 
5, increase production to be carried out step by step, do a comprehensive analysis of various factors, the producing the appropriate production to prevent over-production. 
6, during the operation we should pay attention to all kinds of abnormal conditions timely and make judgments, stop and open the equipment correctly. 
7, in the stable production, record a variety of data display on the instrument, such as temperature, pressure, the current.

Reprinted from: http://www.asphalt-mixing-plants.net/industry-news/asphalt-mixing-plant-process.html

评论

此博客中的热门博文

Characteristics of the concrete pump trailer

Where to find asphalt mixing plant near me

YHZS35 mobile concrete batching plant installed in the Philippines